When it comes to property development and construction finance, progress payments form the backbone of how funds are advanced throughout a project. For lenders like ASAP Finance, this is one of the most critical aspects of loan management – ensuring funds are released only as value is created on site, and almost always on a cost-to-complete basis.
A progress payment or “drawdown” (also known as a DD) refers to the staged release of loan funds throughout the construction or subdivision process. Rather than advancing the entire facility upfront, funds are released progressively as the project reaches agreed milestones. Note, payments are almost always made on a cost-to-complete basis (which we’ve covered in a previous blog How Cost-to-Complete Funding Works in Development ).
This structure ensures borrower equity is applied first to the project and that the lender’s loan facility is sufficient to complete the project.
Every drawdown request is assessed on a simple principle: “after paying the DD request, is the amount being retained by the lender sufficient to complete the project?”.
While there are a range of other considerations when making a payment, the lenders final decision will eventually tie back to that fundamental question.
Before approving a drawdown, prudent lenders will typically consider the following. In most cases, an independent Quantity Surveyor (QS) report will also be required, which addresses many of these points in greater detail.
As mentioned, expect your lender to undertake a site visit. Site inspections are an important step, providing a real-world check against what’s claimed on paper. They also give the lender valuable insight into the quality of workmanship and general site activity. A well-organised, well-resourced and active site signals good project management, while disorganisation or inactivity can indicate emerging risks, unpaid bills or potential delays.
Council inspections play a critical role in the progress payment process, serving as an independent safeguard for both lender and borrower. Each passed inspection verifies that the works completed meet building code requirements.
In a residential build, inspections typically cover key stages such as foundations, framing, and pre-line etc. while subdivision elements focus on civil works such as earthworks, utilities connections, retaining, drainage and driveway (including vehicle crossing) sign offs.
These inspections provide independent assurance that all works are compliant and completed in line with approved plans. They also help confirm there are no outstanding or remedial items that could undermine the project’s cost-to-complete position or the security of the loan.
Green field subdivisions carry their own complexities. Unlike infill projects, where subdivision works are relatively minor and progress can be tracked through defined structural stages, greenfield projects centre on extensive civil and infrastructure works.
Because of this, milestone-based drawdown structures are often impractical. Lenders instead rely on engineering certificates and supporting invoices to verify progress and authorise drawdowns. Given the scale and variability of such works however, QS reporting is almost always required to maintain oversight and cost control.
Unlike traditional banks, ASAP Finance does not require QS reports to fund most projects. Instead, we take a pragmatic, milestone-based approach that streamlines the process without compromising oversight.
Our progress payment schedule is typically structured around clear, definable stages such as foundation, framing, roof on, lock-up, interior completion and so on. Each milestone would correspond to a known percentage of total build cost, making it easier for developers and builders to forecast cashflow and align payments with real progress.
By removing the QS requirement, projects move faster, incur fewer third-party costs, all while maintaining robust checks and balances through council inspection reports and site verification.
A disciplined drawdown process is about more than just compliance – it’s about protecting project viability. By linking payments directly to verified progress and the project’s broader cost-to-complete position, developers maintain stronger control over cashflow, lenders safeguard their exposure, and projects stay on schedule.
ASAP Finance’s model strikes the right balance between efficiency and oversight, ensuring funds are advanced promptly while maintaining the integrity and financial stability of the project.
At ASAP Finance, we view progress payments as prudent management, not an administrative step. Each drawdown is carefully assessed to ensure the project remains in a full cost-to-complete position – protecting momentum, minimising risk, and keeping developments moving forward with confidence.